Programmable Automation Technologies. Daniel Kandray. Читать онлайн. Newlib. NEWLIB.NET

Автор: Daniel Kandray
Издательство: Ingram
Серия:
Жанр произведения: Техническая литература
Год издания: 0
isbn: 9780831191214
Скачать книгу
the production rate (Rp) of the process listed in Example 2.3 in units of parts/hr, assuming the part is produced in batches of 3000 parts and it takes 4 hr to set up the machine to produce the batch.

       Solution

      First, determine the batch production time (tb) and then the average production time (tp). From the average production time, calculate production rate (Rp) in parts/hr. The governing equations are

      tb = tsu + Qtc

      tp = tb/Q

      Rp = 1/tp,

      where the values are

t c = 6.75 min/part (calculated in Example 2.3)
t su = 4 hr
Q = 3000 parts.

      It is important to keep consistent units: convert operational cycle time to units of hr/ part. Thus,

      tc = (6.75 min/part)(1 hr/60 min) = 0.1125 hr/part.

      The batch production time is then

      tb = 4 hr + (3000 parts)(0.1125 hr/part) = 4 hr + 337.5 hr = 341.5 hr.

      The average production time is

      tp = 341.5 hr/3000 parts = 0.1138 hr/part.

      Therefore the production rate is

      Rp = 1/tp = 1/0.1138 hr/part = 8.78 parts/hr.

      The last example highlights how to determine production rate of any type of manufacturing process in which parts are run in batches and setup time is a significant portion of batch production time. As setup time decreases and quantities processed increases, operational cycle time approaches the same value as average production time. This is the case in quantity type manufacturing systems. Thus, the production rate can be determined directly from the operational cycle time:

      tp = tb/Q = (tsu + Qtc)/Q.

      Since setup time becomes small relative to the product of quantity and operational cycle time tc, then clearly

      tp ~ tc.

      Then

      Rpq = 1/tc,

      where

      Rpq = average production rate for a quantity manufacturing systems (parts/min)

      tc = operational cycle time (min/part).

      Calculate the average production rate (Rpq) of the injection molding process in Example 2.4, in units of parts/hr.

       Solution

      The injection molding process is a quantity type manufacturing process. Therefore, the governing equation is

      Rpq = 1/tc.

      Taking the operational cycle time from Example 2.3 and converting the units to hr/ part yields

      tc = (0.334 min/part)(1 hr/60 min) = 0.00567 hr/part.

      Therefore

      Rpq = 1/(0.00567 hr/part) = 179.64 parts/hr.

      Consider the flow-line type manufacturing system shown in Figure 2.1. In it the product is traveling to each workstation via a conveyor belt. At each workstation the product is processed accordingly. Upon completion of the processing, the product is moved to the next station. The transporting of the part is coordinated with the time it takes to complete the processing at each workstation. Some workstations finish processing sooner than others. However, the conveyor cannot move the parts until the slowest process (i.e., the process that takes the most time) is completed. This workstation is called the bottleneck station.

image

      When all the stations have processed the product, it exits the conveyor belt. Thus, at specific time intervals a finished product is produced. The time interval may be expressed in minutes, hours, days, weeks, months, or even years. The production rate has been defined as the number of parts produced per hour, which corresponds to number of parts that drop off the conveyor line in an hour in this example. Therefore, to calculate the production rate it is necessary one determine how often a part falls from the conveyor. This operational cycle time of the flow line (tc) is the sum of the time to move the product between the workstations and the actual processing time at the bottleneck station. In equation form:

      tcf = tr + max to

      where

      tcf = operational cycle time of flow line system (min/part)

      tr = time to transfer parts between stations (min/part)

      max to = actual processing time of bottleneck workstation (parts/min).

      The production rate or cycle rate of the flow line then becomes

      Rc = 1/tcf,

      where Rc = cycle rate of a flow-line manufacturing system (parts/min).

       Example 2.7

      Calculate the cycle rate (Rc) of the flow-line manufacturing system shown in Figure 2-1; assume the transfer rate is 3 sec per part and the processing time for each work station is as shown in the table.

Workstation Processing time (m in/pc)
1 1. 5
2 0. 7 5
3 1. 2 5
4 1. 5
5 0. 5

       Solution

      The governing equations are

      tcf = tr + max to

      Rc = 1/tcf.

      The transfer rate was given as

      tr = 3 sec/part or 0.05 min/part.

      The actual process