The 2017 FIDIC Contracts. William Godwin. Читать онлайн. Newlib. NEWLIB.NET

Автор: William Godwin
Издательство: John Wiley & Sons Limited
Серия:
Жанр произведения: Юриспруденция, право
Год издания: 0
isbn: 9781119514657
Скачать книгу
in clause 3.5 of the 2017 Silver Book is the same as in clause 3.7 of the other two Books, and the qualities of the Employer's Representative, his powers and authority are similar to those of the Engineer, as described in more detail below. One significant difference, however, is that the Employer's Representative is not required to act neutrally in carrying out his duties under clause 3.5 whereas the Engineer is so required, under clause 3.7 of the other two Books; the Employer's Representative is, however, still not to be deemed to act for the Employer in discharging these duties and any determination he makes must also be fair, in accordance with the Contract and take due regard of all relevant circumstances.

      3.2.1 Contract Administration in the Three Books: Engineer's/Employer's Representative's Role and Authority

       The Engineer/Employer's Representative

      Clause 3.1 of the 2017 Red and Yellow Books provides for the appointment of the Engineer and the vesting of all authority necessary to act as the Engineer under the Contract; requirements are also specified for the qualifications and background of the Engineer and fluency in the ruling language as defined in clause 1.4.

      The 1999 Red and Yellow Books provide, by clause 3.1, that the Engineer's staff are to include suitably qualified engineers and other professionals competent to carry out the Engineer's duties, but the 2017 Books go further and provide that the Engineer must be a professional engineer with suitable qualifications, experience and competence and fluent in the language of the Contract.

      Clause 3.1 of the 2017 Red and Yellow Books provides for the Engineer to be a legal entity rather than an individual or firm. If the Engineer is a legal entity, notice of the natural person appointed and authorised to act on its behalf has to be given (clause 3.1, fourth paragraph).

       Authority and duties

      Clause 3.2 of the 2017 Red and Yellow Books sets out the Engineer's duties and authority. He may exercise the authority attributable to the Engineer as specified in or necessarily to be implied from the Contract. If the Engineer is required to obtain the Employer's consent before exercising a specified authority, such a requirement must be stated in the Particular Conditions. However, there is no requirement for the Engineer to obtain the Employer's consent before he exercises his authority under clause 3.7; and the Employer must not impose further constraints on the Engineer's authority. But where the Engineer exercises a specified authority for which the Employer's consent is required, then for the purposes of the Contract such consent is deemed to have been given.

      The 2017 Silver Book (like the 1999 edition) states no similar constraints on the Employer with respect to exercise of his Representative's authority, clause 3.2 in both editions dealing only with delegated authority to assistants.

      Under clause 3.2 of the 2017 Red and Yellow Books any acceptance, agreement, approval, instruction, notice, no‐objection and the like by the Engineer, his representative or any assistant does not relieve the Contractor of any duty, obligation or responsibility which he has under or in connection with the Contract. This provision of clause 3.2 in the 2017 editions is similar to the terms of clause 3.1(c) of the 1999 editions of the Red and Yellow Books.

      Clause 3.3 of the 2017 and 1999 Silver Book relates to delegated persons (including the Employer's Representative) and provides that any approvals, acceptances, notices and the like do not, unless otherwise stated, relieve the Contractor of any of his responsibilities under or in connection with the Contract (see further below).

       Engineer's Representative/assistants

      Clause 3.2 of the 2017 Silver Book provides for the appointment, by a notice to the Contractor, of assistants to whom authority may be delegated by the Employer or Employer's Representative, subject however to the Employer's Representative's being unable to delegate authority to act under clause 3.5 (determinations) or to issue a notice to correct under clause 15.1. Clause 3.3 limits the extent of any delegated authority to what is defined in a notice under clauses 3.1 (relating to the Employer's Representative) or 3.2 (other Employer's personnel) and provides that the Contractor is not to be relieved of any duty or responsibility by a delegated person's (including the Employer's Representative's) acceptance, agreement, approval, instruction, notice, no‐objection and the like (in accordance with the notice of delegation), unless otherwise stated in the delegated person's communication relating to such an act.

      3.2.2 Instructions

      Clause 3.5 of the 2017 Red and Yellow Books and clause 3.4 of the 2017 Silver Book deal with the Engineer's/Employer's instructions in largely the same way. This contrasts with the 1999 editions of the three Books, most noticeably in that in the Red Book the Engineer's instructions did not have to be in writing, although he was meant to give his instructions in writing wherever this was practicable. Provision was then made in clause 3.3 for confirmation of oral instructions, the confirmation then to be taken as constituting the Engineer's written instruction. In the 2017 editions of all three Books instructions must be in writing by virtue of clause 1.3, which expressly provides for instructions to be in writing and to comply with the other requirements of that clause.

      Another difference between the 1999 editions of the three Books is that the instructions which the Engineer, in the Red and Yellow Books, might issue were to be instructions which may be necessary ‘… for the execution of the Works and the remedying of any defects, all in accordance with the Contract’ (clause 3.3). In the 1999 Silver Book, on the other hand, the instructions which the Employer might issue were to be instructions which may be necessary ‘… for the Contractor to perform his obligations under the Contract’ (clause 3.4).

      In the 2017 editions of all three Books this wording has been replaced by a uniform wording: instructions may be issued where they are necessary ‘… for the execution of the Works, all in accordance with the Contract’. Thus the 2017 editions adopt the wording of the 1999 Red and Yellow Books with respect to the scope of instructions under the Contract, deleting however the words ‘… and of the remedying of any defects’.