this is by choosing the right project delivery method to start with.

      What Is Project Delivery?

      Project delivery is the process by which all the procedures and components of designing and building a facility are organized and put together in an agreement that results in a completed project. The process begins with the compilation of needs and requirements of the owner spelled out in the architectural program. These needs and requirements are first expressed in preliminary plans from which initial material, equipment, and systems selections are made. With these selection decisions, the design becomes further refined until all design decisions are made and a final set of contract plans and specifications is completed. The owner then determines which procurement methodology (purchasing steps) to use to buy the construction services and the criteria that will be used to select the contractor. Finally, the owner selects which type of contract to employ. Once selected, the contractor goes about planning an overall strategy for delivering the project in accordance with the plans and specs that have been developed. All the parts and pieces of the agreement are put in place, and the game plan is established.

      This game plan also determines how the players will interact and communicate with one another over the course of the project.

      Types of Project Delivery

      There are basically four primary project delivery methods: design-bid-build, at-risk-construction management, design-build, and integrated project delivery. Keep in mind that the functions associated with construction management are required in all four methods even though only one of them is actually named construction management. As I said earlier, this can get a little confusing.

      These four project delivery methods differ in five fundamental ways:

       The number of contracts the owner executes

       The relationship and roles of each party to the contract

       The point at which the contractor gets involved in the project

       The ability to overlap design and construction

       Who warrants the sufficiency of the plans and specifications

      Regardless of the project delivery method chosen, the three key players—the owner, the designer (architect and/or engineer), and the contractor—are always involved. The traditional roles and responsibilities for the three parties were spelled out in Chapter 1, but keep in mind that the accountabilities and relationships change with the various project delivery methods, as I described in the previous list. And additional players will be added to the project team, usually as subcontracted partners. This will become clearer as you read the individual project delivery descriptions that follow. Each of these methods has specific advantages and disadvantages, and it is the owner's responsibility to assess the project delivery choices in relation to their project needs.

      Design-Bid-Build

      design-bid-build

      A project delivery method in which the owner holds two separate contracts for design and construction. This method is often referred to as the traditional project delivery method.

      Design-bid-build is commonly referred to as the traditional method of project delivery, and the traditional accountabilities apply. In this scenario, the owner first hires the architect or engineer to design the building or structure. The design professional prepares a design, moving through the three standard design phases: schematic design, design development (the design development drawings are often referred to in the industry as DDs), and finally contract documents (referred to as CDs). Under this arrangement, the design professional is usually selected on a qualifications basis and then is typically paid a fee or a percentage of the building cost for their services. (Contract documents will be discussed in greater detail in Chapter 4, “The Construction Contract.”)

      After the plans and specifications are complete, the owner selects the general contractor who will provide the construction and construction management services. The most common means for selecting the general contractor under this method is by low price or low bid: several competing contractors estimate the project based on the contract documents, and the builder with the lowest price gets the contract. The general contractor typically subcontracts various sections of the work to specialty contractors. Under this method, the owner holds two separate contracts, one with the designer and one with the contractor.

Illustration of the design-bid-build method, where the owner holds two separate contracts, one with the designer and one with the contractor. Illustration of the design-bid-build linear approach regarding the design of the project depicting no overlap of design and construction.

      Under the design-bid-build method, the owner warrants the sufficiency of the plans and specs to the contractor. If there are gaps between the plans and specs and the owner's requirements or any errors and omissions in the design, the owner is responsible for paying for those corrections. I mention this because the contractor is often the one who discovers the errors and submits the change orders necessary to correct the work. This is never a happy occasion for the owner. A constructability review, which will be mentioned later, can help prevent such surprises.

      Construction Management

      As you now know, construction management may be viewed from several different perspectives, and one of them is as a specific project delivery method. Under this approach, construction management services are provided to the owner independent of the construction work itself. The owner has two options to choose from as to how they want the CM to interact with the actual construction of the project.

      construction management

      The planning, scheduling, evaluation, and controlling of construction tasks and activities to accomplish specific objectives outlined in the contract documents.

       Option 1: agency CM The Construction Management Association of America (CMAA) defines agency CM as a fee-based service in which the construction manager is responsible exclusively to the owner and acts in the owner's best interests at every stage of the project. In this case, the construction manager offers advice uncolored by any conflicting interest because the construction manager does not perform any of the actual construction work and is not financially at risk for it.agency CMA construction management option in which the construction manager acts in the owner's best interests at every stage of the project from design through construction. In this capacity, the construction manager provides only advice and management